| EQUIPMENT |
SET-UP/WRAP REQUIREMENTS |
FLOORING REQUIREMENTS |
POWER REQUIREMENTS |
ACCESSORIES |
| MIGHTY-MO |
3 days required for set-up & 3 for wrap.*** |
Concrete or welded trench plates *customer provides welder & plates |
300K 480V generator or transformer equivalent |
Positional Plate,
18° increments |
| NACMO |
2 days required for set-up & 2 for wrap.*** |
Concrete or welded trench plates *customer provides welder & plates |
300K 480V generator or transformer equivalent |
Programmable 7th-Axis Motion Rotator & 14' X 30' Deck |
| MINI-MO |
2 days required for set-up & 1 for wrap.*** |
None |
230 Volt, 3 phase, 150 amp service |
360 Rotator |